Client
CIDON
Duration
Start Jan 2026, ongoing
Location
Newcastle
Project Type
25no cores
Wall length/thickness
Cores ranging from 18 to 33 linear metres
Wall Height
Ranging from 13m to 31m high




Construct 25no various size and height cores, a mixture of stair and lift cores over 2 phases. Construction sequencing needed to be planned to suit the groundworks and handover areas, also sequencing the build/dismantle so the cranes and operatives on site to work most efficiently. Cores are planned to be poured one after another, considering crane positions and assemble/dismantle.
Once again Slipform Engineering was involved heavily with rebar detailing, embed plates and other cast it items, reviewing all to suit the slipforming construction method.
Project is due for completion November 2026