Client
CIDON
Duration
2 months
Location
Perth, Scotland
Project Type
Bunker for waste energy facility, design and built using slipforming system
Wall length/thickness
90 linear meters, wall thickness between 700mm and 1400mm with 4no adjoining 1.5x700m & 1no 1.5×1.4 columns 21m high
Wall Height
22.500m


Slipform Engineering provided our client, Cidon, valued engineering solutions to meet their requirements. Once again, project was completed ahead of main construction programme, which we strive and successfully deliver each time. Slipform Engineering team has worked intensively in the pre-construction phase together with clients design team to develop the best possible build solution.
1160m3 of concrete & 165t of reinforcement were used for the build.
Programme: 8 days to complete the build on-site, 4no 24h shifts to place concrete 250mm layers & 5 days to dismantle & demobilize from site.