Client
Affholder / SAK & SHEA JV
Duration
1 year Contract Total
2 weeks River Street Shaft
Location
Austin, Texas
Project Type
Design & delivery of a watertight secondary lining for the River Street Shaft, Austin, Texas. Design and supply of all Slipform Equipment, including management operations, technical & pre-construction provisions.
Shaft heights
23.8 metres
(Up to 60 metres total project)
Wall thickness
38.5 linear metres with
thicknesses of 800mm – 2,000mm
Internal diameter
12.2 metres







River Street Project – Austin, Texas:
Installed a total of 91 metric tonnes of reinforcing steel from the bottom to the top of the shaft, excluding the shaft cover.
Completed three concrete pouring stages, placing a total of 1,093 m³ of concrete across 66 hours of pouring operations.
Stage 1 involved placing 124 m³ over 8 hours, followed by Stage 2, which involved 813 m³ over 50 continuous hours.
Stage 2 required a 12-hour interruption to install substantial box-outs for the future precast roof installation, followed by Stage 2.1, placing a further 156 m³ over 8 hours.
Installed exceptionally large temporary openings during slipforming, engineered to support up to 16 metres of wet concrete head while simultaneously accommodating the slipform jacking system.
Completed the initial slipform rig assembly over 1 week, followed by 1 day of rig adaptation before Stage 2, demonstrating expertise in complex slipform operations and challenging structural requirements.
Total Contract Overview:
Following the successful delivery of the shaft liner works on the Thames Tideway Tunnel Project in London, Slipform Engineering was selected by SAK & Shea JV to support the I-35 Capital Express Central Drainage Tunnel Project in Austin, Texas.
Slipform Engineering’s role included the design and supply of specialist slipform equipment, together with operational management, technical support and pre-construction planning services for the construction of eight reinforced concrete shaft liners along the I-35 corridor through Downtown Austin. The project forms part of a major infrastructure investment aimed at improving flood resilience and supporting the long term development of one of Austin’s busiest transport corridors. With the first shaft nearing completion, Slipform Engineering continues to strengthen its presence within the North American tunnelling and underground infrastructure sector, with further opportunities currently being explored across the United States.